Main MenuGeotechnical EngineeringSpecialized FoundationsSelected ProjectsContainer terminal pavements at new Pier 1 of Piraeus Port Authority at Ιkonio
Project:Container terminal pavements at new Pier 1 of Piraeus Port Authority at Ιkonio
Client:J&P - AVΑX / ΚL. RΟUΤSIS S.Τ.A.
Location:Peiraeus, Greece
Date:4/2008-5/2009
Within the framework of the duties of Technical Consultancy, the geotechnical conditions of both the fill materials and the foundation of the pavement of the existing pier were examined, as well as the densification of the new embankments, till the depth of 20 m, created at the offshore area, for the foundation of the new pavements of the extended section. Works covered a a total area of 35000 m2, of Pier I of P.P.A., in order to create additional container stacking space of a maximum stacking height till 6 containers.
• INSITU - LABORATORY - WORKS
a. Execution of 7 investigation boreholes together with implementation of insitu tests.
b. Execution of insitu plate load tests.
c. Execution of geotechnical and rock-mechanics laboratory tests.
• GEOTECHNICAL STUDIES
a. Geotechnical assessment report
b. Dynamic compaction study report